Sasol 132kV Overhead Powerline Development

Short Project Title

Sasol 132kV Overhead Powerline Development

Project Title

Sasol 132kV Overhead Powerline Development

SRK Project Reference Number

595823

SRK Project Manager

Evert Jacobs

Contact Person

Julia Bell

Contact Email

JBell@srk.co.za

Contact Number

011 441 1111

Sasol

PROJECT SYNOPSIS

Sasol Synfuels Operations is situated near Secunda, in Mpumalanga. As part of the greater Sasol Mulalo project, aimed at making its operations more self-sufficient and aligned with its decarbonisation strategy, Sasol has proposed the development of a powerline to supplement the electricity needs of its Secunda operations. A 132 kV powerline of approximately 5.6 km will be developed, connecting the Eskom Sol Substation to the Sasol Amafutha Substation, transferring, 550 MW from Eskom’s transmission network to Sasol’s Secunda Operations. The project includes the construction of a new 132 kV feeder bay at the Sol substation and a new switch yard at the Amafutha Substation. The construction will occur on already disturbed land with pre-existing infrastructure. It is assumed that the development shall be performed under the Eskom Transmission Self-Build Works process and the environmental authorisation shall be handed over to Eskom upon completion.

 

The proposed powerline will run within an existing Eskom powerline servitude along a wetland, crossing the Bossiesspruit and Kleinspruit rivers at multiple locations along its route. Although the powerline route is through a wetland, the land has been heavily modified from previous activities and developments. The powerline will be completely contained within Sasol Synfuels Secunda Operations secondary area, properties of which are wholly owned by Sasol. The proposed construction of the powerline will be conducted in such a manner as to cause as little destruction/disruption to the wetland and surrounding environment as possible.

 

Sasol has appointed Iyanda Power Technologies (Pty) Ltd (Iyanda) to design and construct the proposed powerline and SRK Consulting (South Africa) (Pty) Ltd (SRK) will undertake the environmental authorisation and water use authorisation process. The proposed powerline project will require a Basic Assessment procedure to be followed in terms of the environmental impact authorisation, as well as a General Authorisation process in terms of water use authorisation. 


PROJECT LOCATION

Sasol Secunda Operations


STATUS OF PROJECT

The project is currently in the public participation phase. The Draft Basic Assessment Report is available for public comment for a period of 30 days. Stakeholders are encouraged to provide written comments to the SRK contact provided above no later than 26 February 2024