Frozen Core Dam Performance: Four Years Post Construction

Authors

Author 1

Author 2

Author 3

Author 4

As part of the tailings management system for the Doris Project in Nunavut Canada, a frozen core dam was constructed in 2012 on a foundation of thick ice-rich, saline glacial marine silt and clay, and fine sand. This dam will not have a tailings beach against it, and as a result has been designed as a water retaining dam for its design life of 20 years. Environmental containment is provided by a frozen core keyed-in, and permanently bonded with the underlying permafrost. To ensure this bond, the engineered (non-saline) frozen core must maintain a temperature below -2°C, and the underlying saline permafrost foundation must be at or below -8°C, under normal operating conditions. To ensure continued successful performance of the dam it has been rigorously instrumented and this paper describe the dam performance four years post construction.